In-House Water Main Replacement Projects

This project will replace 8,000 linear feet of undersized water mains and mains with a history of leaks. Existing pipelines will be upgraded with new 6-inch and 8-inch ductile iron pipe to improve system reliability, increase fire flow capacity, and support the installation of a fire hydrant at the pipeline terminus.

Work will be performed in-house by District water maintenance crews and will require additional staffing.

Project Type

Water

Current Phase

Construction

Estimated Completion

June 2027

Total Project Cost

$1,000,000 (Budgeted Annually)

Water main replacement project

Project Milestones

PROJECT START

June 15, 2026

PHASE 1

Locating Existing Utilities

Current Phase

PHASE 2

Water Main Replacement and Fire Hydrant Installation

PHASE 3

Street Pavement Repairs